Akçansa Cement Co.Inc. "CNK - Line 2 Project 2.0 Million TPY Portland Cement Production Plant" Reinforced concrate system all process structures
Project Design : Civil Engineering
Excavation : 203.000m3
Concrate : 96.500 m3
Formwork : 122.000m2
Slipform : 33.000m2
Reinforcement Steel : 8.500ton
Completed
04-04-2008
Akcansa Cement Co.Inc.
Çanakkale
21.732.071,00.-TL(17.028.734,00 USD)