Çimsa Clinker Producing Plant's Construction Works Construction of Preheater
II.Clinker Production Plant Construction
- Raw Material Bunkers Building and 150t/h Farin Mill
- Preheater Building, Cooling Building
- Clinker Transfer Lines, Cement Mill
- Landscaping (10.000m2 Site Concrete)
II.Clinker Production Plant Steel, Mechanical and Technological Manifacture, Erection Works
- Manifacture and Erection of Preheater Cyclone, Stainless Pipes
- Erection of Preheater Mechanical / Technological Material
- Manifacture and Erection of Preheater Smokestack and Erection of ID Fan Pipe

Total Concrete : 42.500 m3
Total Reinforcement Steel : 3.050 ton
Total Mechanical and Steel Manifacture and Construction : 802 ton
Completed
31-07-2005
Çimsa Cement and Concrete Co.Inc.
Kayseri
5.256.740,00.-TL(3.978.762,00 USD)
Back to Projects List